Capsizing and sinking of the United States Drillship Glomar Java Sea
65 nm S-SW Hainan Island · October 25, 1983
What happened
About 2355 on October 25, 1983, the 400-foot-long United States drillship Glomar Java Sea capsized and sank during Typhoon LEX in the South China Sea about 65 nautical miles south—southwest of Hainan Island,' People's Republic of China. Of the 81 persons who were aboard, 35 bodies have been located, and the remaining 46 persons are missing and presumed dead.
The Glomar Java Sea currently is resting on the bottom of the sea in an inverted position in about 315 feet of water; its estimated value was $35 million.
This accident was investigated jointly by the NTSB and the U.S. Coast Guard with the cooperation of the Bureau of Harbor Superintendents Of the People's Republic of China. Hearings were held in Hong Kong from December 12 to December 14, 1983, and in Houston, Texas, from January 23 to January 30 and on June 13 and June 14, 1984..
Probable cause
We determined that the probable cause of the sinking of the United States drillship Glomar Java Sea during Typhoon LEX was the decision by the master, the Atlantic Richfield Company drilling supervisor, and the Global Marine drilling superintendent to maintain the drillship at anchor at the well site with all nine anchors, which subjected the vessel to the full force of the storm and nllowed it to cepsize to stgrboard as a desult of severe rolling while experiencing a 150 starboard list from an undetermined cause.
Contributing to the large loss of life was the failure of the master, the Atlantie Richfield Company drilling supervisor, and the Global Marine drilling superintendent to evacuate nonessential personnel from the Glomar Java Sea before the weather conditions deteriorated sufficiently to make evacuation dangerous.
What the NTSB recommended
As a result of its investigation, we reiterated the following recommendations issued to the US. Coast Guard on February 28, 1983, as a result of its investigation of the capsizing and sinking of the mobile offshore drillirg unit Ocean Ranger on February 15, 1982:
- Expedite the promulgation of regulations regarding personnel qualifications and manning standards for mobile offshore drilling units. (M-83-8)
- Require that the master and the person-in-charge of a mobile offshore drilling unit be licensed and that their licenses be endorsed as qualified in mobile offshore drilling operations, including knowledge of US. Coast Guard regulations, stability characteristics of mobile offshore drilling units, the operation of ballast systems on mobile offshore drilling units, and the use of equipment peculiar to rnÖbile offshore drilling units. (M-83-9)
- Require that a suitable vessel, capable of retrieving persons from the water under adverse weather eonditions, be assigned to all U.S. mobile offshore drilling units at all times for the purpose of evacuating personnel from the unit in an emergency. (M—83-20)
As a result of its investigation of the Glomar Java Sea, we made the following recommendations:
- --to the Secretary of the U.S. Department of Transportation:
- Direct the Commandant of the U. S. Coast Guard to address immediately the early promulgation of personnel qualification and manning regulations for mobile offshore drilling units. (M-84-48)
—-to the U.S. Coast Guard:
- Revise the stability standards for drillships to include the capability of drillships to survive the flooding of any two adjacent eompartments or tanks located within 5 feet of the hull. (M-84-49)
- Urge the International Maritime Organization to amend its 1979 Code for the Construction and Equipment of Mobile Offshore Drilling Units to include the capability of drillships to survive the flooding of any two adjacent compartments or tanks located within 5 feet of the hull. (M-84—50)
- Require that the operating manual for a include guidance on the degree of survivability to which it is designed and the appropriate countermeasures to be taken in ease of nooding. (M-84-51)
- Amend the U.S. Coast Guard regulations for mobile offshore drilling units (46 CFR 108.503) to require each drillship to have sufficient lifeboats on each side to accommodate all persons onboard. (M-84-53)
- Require as soon as possible that all U.S. Coast Guard-approved survival craft be provided with a radio device capable of A distres signal. (M-84—54)
- Require every inspector (or the senior inspeetor if more than one) assigned to inspect U.S. mobile offshore drilling units in foreign waters to have had prior experience in the inspection of mobile offshore drilling units. (M-84-55)
- Require that a representative sample of nonfuel oil on all US. vessels in saltwater service be inspected internally at least once every 30 months during drydock or biennial inspections and that the sample of tanks to be inspected be increased as the vessel gets older. (M-84-58)
- Require that a representative sample of fuel oil tanks on all US. vessels in saltwater service be inspected internally at least once every 5 years during drydock or biennial inspections and that the sample of tanks to be inspected be increased as the vessel gets older. (M-84-57)
--Global Marine Drillirg Company:
- Designate the master as the individual in overall charge of the ordering, loading, and safe stowage of all drilling equipment, drilling supplies, and ship consumables aboard Global Marine drill-ships. (M-84-68)
- Require that shorebased rig managers of drillships operating in remote areas contact the cognizant rescue coordination center to preplan procedures for an emergency. (M-84-59)
- Provide sufficient licensed personnel severe weather seasons either aboard drillships or ashore nearby to man a drillship operating in a remote area to safely move off location and seek shelter if threatened by a severe storm. (M-84—60)
- Review and revise all heavy weather plans for Global Marine drillships to include a specific list, by position, of nonessential personnel to be evacuated on the approach of a tropical storm, a hurricane, or a typhoon. (M-84—61)
- Review and revise all heavy weather plans for Global Marine drillships to include realistic distance and time guidelines for the evacuation of nonessential personnel, the disconnecting of anchors, and the moving off location on the approach of a tropical storm, a hurricane, or a typhoon, and require that the master take these safety measures when the conditions arise. (M—84-62)
- Review and revise the operating manuals of each Global Marine drillship to include information on its survivability in case of flooding, Actions that should be taken by the master to minimize the effects of flooding, and countermeasures that should be taken by the master in case flooding has occurred. (M-84-63)
- To improve the survivability of drillships, direct all masters, chief engineers, and drilling superintendents that adjacent wing tanks are not to be kept empty. (M—84-64)
- Require representative samples of nonfuel oil tanks on drillships be inspected internally At least onee every 30 months and that representative samples of fuel tanks be inspected internally at least once every 5 years. (M-84—65)
- Install remote gauging systems in all drillships so the engineer on watch can immediately determine the liquid level in all tanks. (M-84-66)
—to ARCO China, Inc:
- Develop a detailed contingency plan for operations off the coast of the People's Republic of China which includes communications procedures; an inventory of air and sea rescue resources and shoreside facilities available for various emergencies, including severe storms; and a requirement to contact the cognizant rescue coordination center to establish procedures for an emergency. (M-84-67)
- Maintain a continuous 24-hour radio watch in the Zhanjiang, People's Republic of China, headquarters to listen for emergency radio transmissions. (M-84-68)
- Consult with the People's Republic of China on maintaining a listening watch in the Zhanjiang headquarters on the international distress frequencies 2182 kHz and 8364 kHz for emergency communications to improve the safety of continuing operations off the coast of the People's Republic of China. (M—84-69)
--to the China National Offshore Oil Company:
- Establish emergency response centers at Tian Du, Zhanjiang, GuArvzhou, and other centers of offshore oil operations which would maintain a continuous listening watch on the international maritime distress frequencies of 2182 kHz and 8364 kHz, as well as the designated operating frequencies, and in time of emergencies would coordinate activities of air and sea rescue resources and shoreside rescue centers. (M-84—70)
- Require an oil eompanies operating off the coast of the People's Republic of China to develop and submit for your review detailed contingency plans which should include eommunieations procedures and an inventory of air and sea rescue resources and shoreside facilities available for various emergencies, including severe storms. (M-84—71)
- Require that a suitable vessel, capable of retrieving persons from the water under adverse conditions, be assigned to all mobile offshore drilling units operating off the coast of the People's Republic of China At all times for the purposes of personnel from the unit in an emergency. (M-84—72)
- Require the standby vessels for a mobile offshore drillirz unit off the coast of the People's Republic of China to maintain a 24—hour radio watch on radio distress and operating frequencies and to use their radar during periods of reduced visibility to maintain contact with the mobile offshore drilling unit. (M-84—73)
—-to the American Bureau of Shipping:
- R evise the stability criteria eontained in the Rules for Building and Classing Mobile Offshore Drilling Units to include the capability of drillships to survive the flooding of any two adjacent compartments or tanks within 5 feet of the hull. (M-84—74)
- Require that a representative sample of nonfuel oil tanks be inspected internally at least once every 30 months for vessels in saltwater service and that the sample of tanks to be inspected be increased as the vessel gets older. (M-84-76)
—to the International Association of Contractors:
- Urge that member contractors review the Chain of command aboard their mobile offshore drilling units to insure that the licensed master or bargemover can effectively exercise full authority over the unit during an emergency. (M-84—77)
- Urge that member eontractors contact the cognizant rescue coordination center to preplan procedures for an emergency involving mobile offshore drilling units in remote locations. (M-84—78)
The current status of each recommendation is on the NTSB's investigation page.
More capsizing investigations
- Capsizing and Sinking of Yacht Bayesian · Near Sicily · Mediterranean Sea, 2024
- Listing and Partial Sinking of Yacht Lovebug · Shady Side, MD · West River, 2024
- Capsizing of Dredging Vessel WB Wood · Meraux, LA · Lower Mississippi River, 2023
- Capsizing of Small Boat from Passenger Vessel World Explorer · Elephant Island, 2022
- Capsizing and Sinking of Fishing Vessel Hotspur · Nunez Point, AK, 2022