Oil and Refining - Fire and Explosion

BP America (Texas City) Refinery Explosion

Texas City, TX · March 23, 2005

What happened

At approximately 1:20 p.m. on March 23, 2005, a series of explosions occurred at the BP Texas City refinery during the restarting of a hydrocarbon isomerization unit. Fifteen workers were killed and 180 others were injured. Many of the victims were in or around work trailers located near an atmospheric vent stack. The explosions occurred when a distillation tower flooded with hydrocarbons and was overpressurized, causing a geyser-like release from the vent stack.

Summary by the US Chemical Safety Board.

Lessons

Hominin's reading of what the investigation asks others to change. Each lesson names the recommendations it comes from.

  1. Keep occupied trailers away from process hazards

    Many of the victims were in or around work trailers near the vent stack. The petroleum institute was asked to revise its building siting guidance so trailers and other temporary structures are placed away from hazardous areas and their occupants protected from blast, heat and projectiles.

    From recommendations 2005-4-I-TX-2, 2005-4-I-TX-3

  2. Startups need more people and more expertise

    BP was asked to add board operator staffing during unit startups, to have knowledgeable supervisors or technically trained staff present during especially hazardous phases, and to keep startup procedures matched to how the unit actually runs.

    From recommendations 2005-4-I-TX-18, 2005-4-I-TX-19, 2005-4-I-TX-20

  3. Stop towers from overfilling

    The explosions followed a distillation tower flooding with hydrocarbons. BP was asked to give towers effective instruments and controls against overfilling, and the relief system guidance was asked to treat vessel overfilling as a hazard to design for.

    From recommendations 2005-4-I-TX-14, 2005-4-I-TX-4

  4. Measure process safety, not only injury rates

    BP's board was asked to make senior executives use leading and lagging process safety indicators, and a new national standard was asked for to define such indicators for refineries and petrochemical plants.

    From recommendations 2005-4-I-TX-13, 2005-4-I-TX-6

  5. Organizational changes need a safety review too

    Process safety guidance and the federal standard were asked to bring mergers, reorganizations, budget changes and staffing changes under management of change, the review normally applied to changes in equipment and chemistry.

    From recommendations 2005-4-I-TX-10, 2005-4-I-TX-9

Safety recommendations

The CSB made 26 recommendations; 1 is still open.

To American Petroleum Institute (API)

  • 2005-4-I-TX-2Closed - Acceptable Action

    In light of the findings concerning the March 23rd incident at BP's Texas City refinery, revise your Recommended Practice 752, Management of Hazards Associated with Location of Process Plant Buildings or issue a new Recommended Practice to ensure the safe placement of occupied trailers and similar temporary structures away from hazardous areas of process plants. Ensure that the new recommended practice: - Protects occupants from accident hazards such as heat, blast overpressure, and projectiles; - Establishes minimum safe distances for trailers and similar temporary structures away from hazardous areas of process plants; and - Evaluates the siting of trailers under a separate methodology from permanent structures, since trailers are more susceptible to damage, are more readily relocated, and likely do not need to be placed near hazardous areas.

  • 2005-4-I-TX-3Closed - Acceptable Action

    Issue a safety alert to your membership to take prompt action to ensure the safe placement of occupied trailers away from hazardous areas of process plants.

  • 2005-4-I-TX-4Closed - Acceptable Action

    Revise API Recommended Practice 521, Guide for Pressure Relieving and Depressurizing Systems to ensure that the guidelines: - Identifies overfilling vessels as a potential hazard for evaluation in selecting and designing pressure relief and disposal systems; - Addresses the need to adequately size disposal drums for credible worse-case liquid relief scenarios, based on accurate relief valve and disposal collection piping studies; and - Warns against the use of atmospheric blowdown drums and stacks attached to collection piping systems that receive flammable discharges from multiple relief valves and urges the use of appropriate inherently safer alternatives such as a flare system

  • 2005-4-I-TX-6Closed - Acceptable Alternative Action

    Develop a new consensus American National Standards Institute (ANSI) standard that creates performance indicators for process safety in the refinery and petrochemical industries. Ensure that the standard identifies leading and lagging indicators for nationwide public reporting as well as indicators for use at individual facilities. Include methods for the development and use of the performance indicators. Ensure that: a. the committees are accredited and conform to ANSI principles of openness, balance, due process, and consensus; b. include representation of diverse sectors such as industry, labor, government, public interest and environmental organizations and experts from relevant scientific organizations and disciplines.

  • 2005-4-I-TX-7Closed - Acceptable Action

    Develop a new consensus American National Standards Institute (ANSI) standard with fatigue prevention guidelines for the refining and petrochemical industries that, at a minimum, limit hours and days of work and address shift work. In the development of the standard, ensure that the committees: a. are accredited and conform to ANSI principles of openness, balance, due process, and consensus; b. include representation of diverse sectors such as industry, labor, government, public interest and environmental organizations and experts from relevant scientific organizations and disciplines.

To BP Global Executive Board of Directors

  • 2005-4-I-TX-1Closed - Acceptable Action

    Commission an independent panel to assess and report on the effectiveness of BP North America's corporate oversight of safety management systems at its refineries and its corporate safety culture. Provide the panel with necessary funding, resources, and authority - including full access to relevant data, corporate records, and employee interviews - in order to conduct a thorough, independent, and credible inquiry. Ensure that, at a minimum, the panel report examines and recommends any needed improvements to: Corporate safety oversight, including the safe management of refineries obtained through mergers and acquisitions; Corporate safety culture, including the degree to which: - Corporate officials exercise appropriate leadership to promote adherence to safety management systems; - Process safety is effectively incorporated into management decisionmaking at all levels; - Employees at all levels are empowered to promote improved process safety; - Process safety programs receive adequate resources and are appropriately positioned within organizational structures; Corporate and site safety management systems, specifically: - Near-miss reporting and investigation programs; - Mechanical integrity programs; - Hazard analysis programs, management-of-change programs, and up-todate operating procedures for processes with catastrophic potential; - Siting policies for occupied structures near hazardous operating units. Ensure that the panel has a diverse makeup, including an external chairperson; employee representatives; and outside safety experts, such as experts in process safety; experts in corporate culture, organizational behavior, and human factors; and experts from other high-risk sectors such as aviation, space exploration, nuclear energy, and the undersea navy. Ensure that the report and recommendations of the independent panel, which should be completed within 12 months, are made available to the BP workforce and to the public.

  • 2005-4-I-TX-11Closed - Acceptable Alternative Action

    Appoint an additional non-executive member of the Board of Directors with specific professional expertise and experience in refinery operations and process safety. Appoint this person to be a member of the Board Ethics and Environmental Assurance Committee.

  • 2005-4-I-TX-12Closed - Acceptable Action

    Ensure and monitor that senior executives implement an incident reporting program throughout your refinery organization that: a. encourages the reporting of incidents without fear of retaliation; b. requires prompt corrective actions based on incident reports and recommendations, and tracks closure of action items at the refinery where the incident occurred and other affected facilities; and c. requires communication of key lessons learned to management and hourly employees as well as to the industry.

  • 2005-4-I-TX-13Closed - Acceptable Action

    Ensure and monitor that senior executives use leading and lagging process safety indicators to measure and strengthen safety performance in your refineries.

To BP Texas City Refinery

  • 2005-4-B-TX-1Closed - Acceptable Action

    Revise the maintenance quality control program to require positive material identification testing or another suitable material verification process for all critical service alloy steel piping components removed and reinstalled during maintenance and inform work crews of special material handling precautions.

  • 2005-4-I-TX-14Closed - Acceptable Action

    Evaluate your refinery process units to ensure that critical process equipment is safely designed. At a minimum: a. Ensure that distillation towers have effective instrumentation and control systems to prevent overfilling such as multiple level indicators and appropriate automatic controls. b. Configure control board displays to clearly indicate material balance for distillation towers.

  • 2005-4-I-TX-15Closed - Acceptable Action

    Ensure that instrumentation and process equipment necessary for safe operation is properly maintained and tested. At a minimum: a. Establish an equipment database that captures the history of testing, inspections, repair, and successful work order completion. b. Analyze repair trends and adjust maintenance and testing intervals to prevent breakdowns. c. Require repair of malfunctioning process equipment prior to unit startups.

  • 2005-4-I-TX-16Closed - Acceptable Action

    Work with the United Steelworkers Union and Local 13-1 to establish a joint program that promotes the reporting, investigation, and analysis of incidents, near-misses, process upsets, and major plant hazards without fear of retaliation. Ensure that the program tracks recommendations to completion and shares lessons learned with the workforce.

  • 2005-4-I-TX-17Closed - Acceptable Action

    Improve the operator training program. At a minimum, require: a. face-to-face training conducted by personnel with process-specific knowledge and experience who can assess trainee competency, and; b. training on recognizing and handling abnormal situations including the use of simulators or similar training tools.

  • 2005-4-I-TX-18Closed - Acceptable Action

    Require additional board operator staffing during the startup of process units. Ensure that hazard reviews address staffing levels during abnormal conditions such as startups, shutdowns, and unit upsets.

  • 2005-4-I-TX-19Closed - Acceptable Action

    Require knowledgeable supervisors or technically trained personnel to be present during especially hazardous operation phases such as unit startup.

  • 2005-4-I-TX-20Closed - Acceptable Action

    Ensure that process startup procedures are updated to reflect actual process conditions.

To Center for Chemical Process Safety (CCPS)

  • 2005-4-I-TX-10Closed - Acceptable Action

    Issue management of change guidelines that address the safe control of the following: a. major organizational changes including mergers, acquisitions, and reorganizations; b. changes in policies and budgets; c. personnel changes; and d. staffing during process startups, shutdowns and other abnormal conditions.

To JV Industrial Companies

  • 2005-4-B-TX-2Closed - Acceptable Action

    Develop / update the written piping component installation quality control procedure to require positive material identification testing or other suitable verification or tracking process for all alloy steel piping components removed during maintenance.

To National Petrochemical and Refiners Association (NPRA)

  • 2005-4-I-TX-3Closed - Acceptable Action

    Issue a safety alert to your membership to take prompt action to ensure the safe placement of occupied trailers away from hazardous areas of process plants.

To Occupational Safety and Health Administration (OSHA)

  • 2005-4-I-TX-5Closed - Acceptable Action

    Implement a national emphasis program for all oil refineries that focuses on: - The hazards of blowdown drums and stacks that release flammables to the atmosphere instead of to an inherently safer disposal system such as a flare. Particular attention should be paid to blowdown drums attached to collection piping systems servicing multiple relief valves; - The need for adequately sized disposal knockout drums to safely contain discharged flammable liquid based on accurate relief valve and disposal collection piping studies Urge states that administer their own OSHA plan to implement comparable emphasis programs within their respective jurisdictions.

  • 2005-4-I-TX-8Closed - Acceptable Alternative Action

    Strengthen the planned comprehensive enforcement of the OSHA Process Safety Management (PSM) standard. At a minimum: a. Identify those facilities at greatest risk of a catastrophic accident by using available indicators of process safety performance and information gathered by the EPA under its Risk Management Program (RMP). b. Conduct, or have conducted, comprehensive inspections, such as those under your Program Quality Verification (PQV) program at facilities identified as presenting the greatest risk. c. Establish the capacity to conduct more comprehensive PSM inspections by hiring or developing a sufficient cadre of highly trained and experienced inspectors. d. Expand the PSM training offered to inspectors at the OSHA National Training Institute.

  • 2005-4-I-TX-9Open - Unacceptable Response/No Response Received

    Amend the OSHA PSM standard to require that a management of change (MOC) review be conducted for organizational changes that may impact process safety including: a. major organizational changes such as mergers, acquisitions, or reorganizations; b. personnel changes, including changes in staffing levels or staff experience; and c. policy changes such as budget cutting.

To United Steelworkers of America (USWA)

  • 2005-4-I-TX-6Closed - Acceptable Action

    Work with API to develop a new consensus American National Standards Institute (ANSI) standard that creates performance indicators for process safety in the refinery and petrochemical industries. Ensure that the standard identifies leading and lagging indicators for nationwide public reporting as well as indicators for use at individual facilities. Include methods for the development and use of the performance indicators.

  • 2005-4-I-TX-7Closed - Acceptable Action

    Work with API to develop a new consensus American National Standards Institute (ANSI) standard with fatigue prevention guidelines for the refining and petrochemical industries that, at a minimum, limit hours and days of work and address shift work.

To USW Local 13-1

  • 2005-4-I-TX-21Closed - Acceptable Action

    Work with BP to establish a joint program that promotes reporting, investigating, and analyzing incidents, near-misses, process upsets, and major plant hazards without fear of retaliation. Ensure that the program tracks recommendations to completion and shares lessons learned with the workforce.